Actions with a specification sheet
Actions with a specification sheet are available in the sheet context menu (three-dot icon next to the sheet name).
They allow you to manage the structure of the specification and perform operations with sheets.

How estimate and specification sheets are paired
The estimate and the specification are built the same way: in both, work is done on sheets. An estimate sheet and the specification sheet with the same name form a pair.
While the specification is in a status before disconnection, pairs are created automatically: add a sheet in the estimate and the same sheet appears in the specification.
Once the specification reaches a status with Disconnection enabled, the automatic link is switched off: the warehouse works with its own version of the composition, and new estimate sheets no longer reach the specification. The estimate then shows the warning “Attention! Work has begun in the Specification”, while the specification records it in the “Information about the manager’s work” block — “A new sheet with the name … has been added”.
Please note: the status at which disconnection is enabled is set in the global settings — the gear icon «Settings» → «System» → «Statuses» → the specification statuses block, the “Disconnection” column. By default this is the second specification status.
That is why the items in the sheet menu depend on whether the sheet has a pair in the estimate:
it has a pair — the menu shows Update Composition;
it has no pair — the menu shows Copy to estimate instead.
Booking time
The Booking time action allows you to set or change the reservation period for all equipment in the sheet.
Important:
the booking time can extend beyond the project dates
the new time is applied to all equipment in the sheet
If needed, you can go deeper:
expand the list down to the SKU level
set booking time for specific units only
Changing the booking time affects only equipment availability and does not affect the estimate.
Update Composition
The Update Composition action synchronizes the specification with the estimate.
If changes were made in the estimate but were not reflected in the specification (desynchronization), this action:
aligns the specification with the estimate
effectively rebuilds the specification based on the current estimate
After applying this action, the sheet structure and content will match the estimate.
Copy to estimate
The item appears for a specification sheet that has no paired sheet in the estimate — for example, when the warehouse created the sheet after disconnection.
The action creates a sheet in the estimate with the same name and the same entries.
After copying, the sheets become a pair: the specification menu shows “Update Composition” instead of “Copy to estimate”, and the estimate menu shows “Update from specification”.
Copy sheet
The Copy sheet action creates a duplicate of the current sheet within the same project.
The copy includes:
structure (sections and subsections)
all entries
comments
This is useful for creating variations or reusing the same setup.
Copying the sheet to…
The Copying the sheet to… action allows you to copy the sheet to another project within the same account.
When copying:
structure is preserved
entries are preserved
comments are preserved
A new sheet will be created in the selected project.
Rename
Allows you to change the sheet name.
Remove
Deletes the sheet from the project.
Important:
this action is irreversible
it affects warehouse-related documents (e.g., picking/warehouse lists)
it does not affect the estimate, as documents like quotations are based on the estimate
Key concepts: